How to Design Backup Power Systems Using Generators and ATS

Learn how to design backup power systems using generators and ATS with load calculations, sizing methods, examples, and best practices.


In modern electrical infrastructure, uninterrupted power supply is critical for residential buildings, commercial facilities, hospitals, data centers, and industrial plants. Power outages can lead to financial losses, safety risks, data corruption, and operational downtime. A well-designed backup power system using generators and an Automatic Transfer Switch (ATS) ensures continuity of electrical supply during utility failures.

This article provides a comprehensive, step-by-step technical guide on how to design backup power systems. It covers load assessment, generator sizing, ATS selection, system configuration, calculations, real-world examples, and best engineering practices. By the end, readers will have a clear, practical understanding of professional backup power system design.


1. Understanding Backup Power Systems

A backup power system is an independent electrical supply that automatically or manually provides power when the main utility source fails. The core components include:

  • Generator (Diesel, Gas, or Hybrid)
  • Automatic Transfer Switch (ATS)
  • Main Distribution Board (MDB)
  • Fuel System
  • Control and Protection Devices

When utility power is lost, the ATS detects the failure, starts the generator, and transfers the load. Once utility power is restored, the ATS switches back and shuts down the generator safely.


2. Types of Backup Power Systems

2.1 Emergency Power Systems (EPS)

Used in hospitals, fire protection systems, and life-safety loads. These systems must comply with strict standards (IEC, NEC, NFPA).

2.2 Standby Power Systems

Common in residential and commercial buildings to maintain comfort and business continuity.

2.3 Prime Power Systems

Used where utility power is unreliable or unavailable. The generator operates for extended durations.


3. Load Assessment and Classification

Accurate load calculation is the foundation of backup power system design. Loads are typically classified as:

  • Critical Loads – Must operate during outages (emergency lighting, servers)
  • Essential Loads – Important but not life-critical (HVAC, elevators)
  • Non-Essential Loads – Can be disconnected during outages

3.1 Load Calculation Method

Total connected load is calculated using:

Total Load (kW) = Σ (Rated Power × Demand Factor)

For motors, starting current must be considered due to high inrush currents.


4. Generator Sizing – Technical Calculation

4.1 Basic Generator Sizing Formula

Generator capacity is usually specified in kVA. The relationship between kW and kVA is:

kVA = kW / Power Factor

Typical power factor values:

  • Residential: 0.8
  • Commercial: 0.85
  • Industrial: 0.9

4.2 Example Calculation

Assumptions:

  • Total essential load = 120 kW
  • Average power factor = 0.85
  • Future growth margin = 20%

Step 1: Calculate kVA

kVA = 120 / 0.85 = 141.18 kVA

Step 2: Add future margin

Required Generator Size = 141.18 × 1.2 ≈ 170 kVA

Therefore, a 180 kVA generator would be selected as a standard rating.


5. Motor Starting and Transient Load Analysis

Motors draw 5–7 times their rated current during startup. This causes voltage dips that must be within acceptable limits.

Engineers must analyze:

  • Largest motor starting kVA
  • Simultaneous motor starting
  • Generator transient response

Soft starters or VFDs can significantly reduce generator size by limiting inrush current.


6. Automatic Transfer Switch (ATS) Selection

6.1 ATS Types

  • Open Transition ATS – Break-before-make (most common)
  • Closed Transition ATS – Make-before-break (no interruption)
  • Manual Transfer Switch – Human-operated

6.2 ATS Rating Calculation

ATS current rating must be higher than the full-load current:

Current (A) = (kVA × 1000) / (√3 × Voltage)

Example:

Current = (180 × 1000) / (1.732 × 400) ≈ 260 A

A 315 A or 400 A ATS would be selected for safety and future expansion.


7. System Configuration and Single-Line Diagram

A critical aspect of designing a backup power system is its system configuration and the corresponding single-line diagram (SLD). The configuration determines how power flows from both the utility and the generator to the loads, ensures smooth automatic transfer, and maintains safety and reliability during outages.

7.1 Typical Backup Power System Configuration

A standard backup system generally includes two main power sources and a transfer mechanism:

  • Utility Supply → Automatic Transfer Switch (ATS) → Main Distribution Board (MDB)
  • Generator → Automatic Transfer Switch (ATS) → Emergency Load Panel (ELP)

In this setup:

  • The utility supply provides power under normal conditions to the building loads.
  • The generator serves as the backup power source during utility failure.
  • The ATS monitors the utility voltage and frequency, automatically disconnects the utility when it fails, starts the generator, and transfers the load to ensure uninterrupted supply.

7.2 Single-Line Diagram (SLD)

The single-line diagram is a simplified representation of the electrical system showing the main components and their interconnections. For backup power systems, an SLD helps engineers to:

  • Visualize the power flow from both sources to the loads.
  • Identify protection devices, switchgear, and load segregation.
  • Plan for proper maintenance and fault isolation procedures.

A typical SLD for a backup power system includes:

  • Utility incomer breaker
  • ATS with input from utility and generator
  • Generator breaker and control panel
  • Main Distribution Board (MDB) feeding critical and non-critical loads
  • Emergency Load Panel (ELP) for essential loads
  • Protective devices such as MCCBs, fuses, and relays

7.3 Key Design Considerations

When designing the system and SLD, engineers must carefully consider:

  • Neutral Switching Strategy: Decide between 3-pole and 4-pole ATS. A 3-pole ATS switches only the phase lines, leaving the neutral common, which is suitable for most systems. A 4-pole ATS switches both phase and neutral, necessary when the neutral is isolated or when dealing with harmonics or unbalanced loads.
  • Grounding and Bonding: Proper grounding ensures personnel safety, protects equipment, and stabilizes voltage during faults. Both the generator frame and ATS must be correctly bonded to the building grounding system.
  • Short-Circuit Withstand Rating: Switchgear, breakers, and ATS components must have adequate short-circuit ratings to safely handle prospective fault currents without damage. This protects both the generator and building loads during fault conditions.
  • Load Segregation: Separate essential and non-essential loads to prevent overloading the generator and optimize runtime during prolonged outages.
  • Voltage Drop Considerations: Ensure cable sizes and distances are calculated to minimize voltage drops, especially for critical loads.

By carefully planning the configuration and single-line diagram, engineers ensure the backup system is reliable, safe, and capable of handling both normal operation and emergency conditions efficiently.


8. Fuel System and Runtime Calculation

Fuel autonomy is critical for extended outages.

Fuel Consumption (L/hr) ≈ 0.24 × Generator kW

Example:

Fuel Consumption = 0.24 × 120 = 28.8 L/hr

For 8 hours of backup:

Fuel Required = 28.8 × 8 = 230.4 Liters

9. Protection, Safety, and Compliance

A professional design must comply with applicable standards:

  • IEC 60364
  • NEC (NFPA 70)
  • ISO 8528 (Generators)

Protection devices include:

  • Overcurrent protection
  • Earth fault protection
  • Reverse power protection
  • Emergency stop circuits

10. Testing and Commissioning

Before commissioning, the system must undergo:

  • No-load testing
  • Load bank testing
  • ATS functional testing
  • Voltage and frequency stability checks

Regular maintenance ensures long-term reliability.


11. Common Design Mistakes to Avoid

  • Under-sizing generators
  • Ignoring motor starting current
  • Improper grounding design
  • Incorrect ATS rating
  • No future expansion margin

FAQs – Backup Power System Design

Q1: How do I choose between diesel and gas generators?

Diesel generators offer higher reliability and better transient response, while gas generators are cleaner and suitable for continuous operation.

Q2: Is ATS mandatory for backup power systems?

For critical and emergency systems, ATS is essential to ensure automatic and safe power transfer.

Q3: Can one generator supply multiple ATS units?

Yes, but load coordination and protection must be carefully designed to prevent overload.

Q4: How often should backup systems be tested?

Monthly no-load tests and annual full-load tests are recommended.

Q5: What margin should be kept for future expansion?

A margin of 15–25% is commonly used in professional designs.


Conclusion

Designing a backup power system using generators and ATS requires a systematic engineering approach. Accurate load analysis, proper generator sizing, correct ATS selection, and compliance with standards are essential for reliability and safety. When designed correctly, backup power systems provide uninterrupted operation, protect assets, and ensure peace of mind during power outages.

This guide serves as a complete reference for electrical engineers, consultants, and system designers aiming to implement high-quality, future-proof backup power solutions.